When do I need to order everything for my renovation?
Pick your project and your start date. We'll turn real lead times into an order-by date for every item — so nothing puts your project on hold. Free, no sign-up.
11 of 38 items need to be ordered before work starts — and 2 are already past their order-by date for this start date.
Rough-In and Framing
phase starts Dec 25, 2026
- Windowsorder by Sep 26, 2026 · order now
- Cement board (behind backsplash)order by Dec 11, 2026
Insulation, Drywall, and Paint
phase starts Jan 2, 2027
- Insulationorder by Dec 19, 2026
- Drywall / drywall repairsorder by Dec 19, 2026
- Wall paintorder by Dec 31, 2026
- Ceiling paintorder by Dec 31, 2026
- Trim paintorder by Dec 31, 2026
- Caulk / touch-up paintorder by Dec 31, 2026
Flooring
phase starts Jan 11, 2027
- Flooringorder by Dec 12, 2026
- Grout (if using tile)order by Jan 6, 2027
Cabinetry
phase starts Jan 15, 2027
- Cabinets (uppers + lowers)order by Sep 17, 2026 · order now
- Drawer slidesorder by Jan 1, 2027
- Cabinet pulls & knobsorder by Jan 1, 2027
- Doors (interior)order by Jan 1, 2027
- Trim / crown moldingorder by Jan 1, 2027
- Door hardware / knobs / leversorder by Jan 1, 2027
- Under-cabinet lighting (mount channels)order by Jan 1, 2027
- Recessed ceiling lightsorder by Jan 1, 2027
- Island pendantsorder by Jan 1, 2027
- Switches & GFCI outletsorder by Jan 1, 2027
- Outlet covers / switch platesorder by Jan 10, 2027
Countertops and Backsplash
phase starts Jan 21, 2027
- Countertoporder by Nov 22, 2026
- Backsplash tileorder by Dec 22, 2026
Fixtures and Appliance Installation
phase starts Jan 31, 2027
- Rangeorder by Nov 2, 2026
- Wall ovenorder by Nov 2, 2026
- Cooktoporder by Nov 2, 2026
- Refrigeratororder by Nov 2, 2026
- Kitchen sinkorder by Jan 17, 2027
- Kitchen faucetorder by Jan 17, 2027
- Prep/bar sinkorder by Jan 17, 2027
- Pot fillerorder by Jan 17, 2027
- Garbage disposalorder by Jan 17, 2027
- Range hood / ventilationorder by Jan 17, 2027
- Microwaveorder by Jan 17, 2027
- Dishwasherorder by Jan 17, 2027
- Under-cabinet lighting (final hookup)order by Jan 17, 2027
- Sink task lightorder by Jan 17, 2027
- Window treatments / blinds / shades / curtainsorder by Jan 17, 2027
Dates change. Your plan should change with them.
Save this plan as a free Hausbound project: check items off as you order, forward order emails to auto-track deliveries, and every order-by date recomputes when your schedule moves.
Save my plan — freeor get the app on your phoneKnow someone else mid-renovation? Send them this plan — it opens the same free tool with these dates already filled in.
Planning a basement, laundry room, home office, or another project? Those templates — with the same order-by engine — are included with Hausbound's unlocked plans.
How this works
Your start date sets when each build phase begins, and every item's order-by date is worked backward from the phase that needs it, using conservative lead times — the full method is in the renovation ordering timeline.
What's different here: these are one-time estimates, but inside Hausbound the same engine recomputes your dates automatically when your schedule moves, your retailer quotes a different lead time, or an order email lands in your Hausbound Mailbox.