When do I need to order everything for my renovation?

Pick your project and your start date. We'll turn real lead times into an order-by date for every item — so nothing puts your project on hold. Free, no sign-up.

13 of 41 items need to be ordered before work starts — and 2 are already past their order-by date for this start date.

📬 Email me this plan, and remind me when each order is due

You get these order-by dates in your inbox now, then one short reminder in the week each item needs ordering. Nothing else, and you can unsubscribe any time.

Insulation and Drywall

phase starts Nov 16, 2026

  • Insulationorder by Nov 2, 2026
  • Drywall / drywall repairsorder by Nov 2, 2026

Waterproofing and Framing

phase starts Nov 20, 2026

  • Shower pan / linerorder by Nov 6, 2026
  • Cement board (shower walls)order by Nov 6, 2026
  • Waterproofing membraneorder by Nov 6, 2026

Tile and Flooring

phase starts Nov 23, 2026

  • Shower wall tileorder by Oct 24, 2026
  • Shower floor tileorder by Oct 24, 2026
  • Bathroom floor tileorder by Oct 24, 2026
  • Vanity backsplash tileorder by Oct 24, 2026
  • Groutorder by Nov 18, 2026

Vanity, Toilet, and Fixtures

phase starts Nov 30, 2026

  • Shower enclosure / glass doororder by Sep 1, 2026 · order now
  • Tub / bathtuborder by Sep 1, 2026 · order now
  • Vanityorder by Oct 1, 2026
  • Vanity countertop / vanity toporder by Oct 1, 2026
  • Sink(s)order by Nov 16, 2026
  • Sink faucet(s)order by Nov 16, 2026
  • Medicine cabinet / mirrororder by Nov 16, 2026
  • Storage cabinet(s) / shelvesorder by Nov 16, 2026
  • Cabinet hardware / pulls / knobsorder by Nov 16, 2026
  • Showerheadorder by Nov 16, 2026
  • Shower handles / valveorder by Nov 16, 2026
  • Shower drainorder by Nov 16, 2026
  • Bathtub faucetorder by Nov 16, 2026
  • Exhaust / vent fanorder by Nov 16, 2026
  • Vanity light fixtureorder by Nov 16, 2026
  • Ceiling light fixtureorder by Nov 16, 2026
  • Toiletorder by Nov 25, 2026
  • Shower curtain rodorder by Nov 25, 2026
  • Toilet paper holderorder by Nov 25, 2026
  • Towel bar(s)order by Nov 25, 2026
  • Robe hooksorder by Nov 25, 2026
  • Grab barsorder by Nov 25, 2026

Paint and Finishes

phase starts Dec 5, 2026

  • Door hardware / knobs / leversorder by Nov 21, 2026
  • Window treatments / blinds / shades / curtainsorder by Nov 21, 2026
  • Outlet covers / switch platesorder by Nov 30, 2026
  • Shower curtain / rodorder by Nov 30, 2026
  • Wall paintorder by Dec 3, 2026
  • Ceiling paintorder by Dec 3, 2026
  • Door paintorder by Dec 3, 2026
  • Trim paintorder by Dec 3, 2026
  • Caulk (tub, shower, vanity)order by Dec 3, 2026

Dates change. Your plan should change with them.

Save this plan as a free Hausbound project: check items off as you order, forward order emails to auto-track deliveries, and every order-by date recomputes when your schedule moves.

Save my plan — freeor get the app on your phone

Know someone else mid-renovation? Send them this plan — it opens the same free tool with these dates already filled in.

Planning a basement, laundry room, home office, or another project? Those templates — with the same order-by engine — are included with Hausbound's unlocked plans.

How this works

Your start date sets when each build phase begins, and every item's order-by date is worked backward from the phase that needs it, using conservative lead times — the full method is in the renovation ordering timeline.

What's different here: these are one-time estimates, but inside Hausbound the same engine recomputes your dates automatically when your schedule moves, your retailer quotes a different lead time, or an order email lands in your Hausbound Mailbox.