When do I need to order everything for my renovation?
Pick your project and your start date. We'll turn real lead times into an order-by date for every item — so nothing puts your project on hold. Free, no sign-up.
11 of 38 items need to be ordered before work starts — and 2 are already past their order-by date for this start date.
Rough-In and Framing
phase starts Nov 7, 2026
- Windowsorder by Aug 9, 2026 · order now
- Cement board (behind backsplash)order by Oct 24, 2026
Insulation, Drywall, and Paint
phase starts Nov 15, 2026
- Insulationorder by Nov 1, 2026
- Drywall / drywall repairsorder by Nov 1, 2026
- Wall paintorder by Nov 13, 2026
- Ceiling paintorder by Nov 13, 2026
- Trim paintorder by Nov 13, 2026
- Caulk / touch-up paintorder by Nov 13, 2026
Flooring
phase starts Nov 24, 2026
- Flooringorder by Oct 25, 2026
- Grout (if using tile)order by Nov 19, 2026
Cabinetry
phase starts Nov 28, 2026
- Cabinets (uppers + lowers)order by Jul 31, 2026 · order now
- Drawer slidesorder by Nov 14, 2026
- Cabinet pulls & knobsorder by Nov 14, 2026
- Doors (interior)order by Nov 14, 2026
- Trim / crown moldingorder by Nov 14, 2026
- Door hardware / knobs / leversorder by Nov 14, 2026
- Under-cabinet lighting (mount channels)order by Nov 14, 2026
- Recessed ceiling lightsorder by Nov 14, 2026
- Island pendantsorder by Nov 14, 2026
- Switches & GFCI outletsorder by Nov 14, 2026
- Outlet covers / switch platesorder by Nov 23, 2026
Countertops and Backsplash
phase starts Dec 4, 2026
- Countertoporder by Oct 5, 2026
- Backsplash tileorder by Nov 4, 2026
Fixtures and Appliance Installation
phase starts Dec 14, 2026
- Rangeorder by Sep 15, 2026
- Wall ovenorder by Sep 15, 2026
- Cooktoporder by Sep 15, 2026
- Refrigeratororder by Sep 15, 2026
- Kitchen sinkorder by Nov 30, 2026
- Kitchen faucetorder by Nov 30, 2026
- Prep/bar sinkorder by Nov 30, 2026
- Pot fillerorder by Nov 30, 2026
- Garbage disposalorder by Nov 30, 2026
- Range hood / ventilationorder by Nov 30, 2026
- Microwaveorder by Nov 30, 2026
- Dishwasherorder by Nov 30, 2026
- Under-cabinet lighting (final hookup)order by Nov 30, 2026
- Sink task lightorder by Nov 30, 2026
- Window treatments / blinds / shades / curtainsorder by Nov 30, 2026
Dates change. Your plan should change with them.
Save this plan as a free Hausbound project: check items off as you order, forward order emails to auto-track deliveries, and every order-by date recomputes when your schedule moves.
Save my plan — freeor get the app on your phoneKnow someone else mid-renovation? Send them this plan — it opens the same free tool with these dates already filled in.
Planning a basement, laundry room, home office, or another project? Those templates — with the same order-by engine — are included with Hausbound's unlocked plans.
How this works
Your start date sets when each build phase begins, and every item's order-by date is worked backward from the phase that needs it, using conservative lead times — the full method is in the renovation ordering timeline.
What's different here: these are one-time estimates, but inside Hausbound the same engine recomputes your dates automatically when your schedule moves, your retailer quotes a different lead time, or an order email lands in your Hausbound Mailbox.