The order of a bathroom remodel: what goes first, and what waits

A full bathroom remodel runs in eleven steps: choose and order, demo, framing and blocking, rough plumbing and electrical, rough inspection, set the tub, wall board and waterproofing, tile, paint, fixtures, and last the shower glass and final caulk. The order is not a preference; each step hides the one before it. The one that decides everything is rough plumbing, because the shower valve depth, the drain position and the supply heights come from a vanity, a tub and a valve you have to have chosen before the walls are open. Below: the sequence with what each step waits for, the four questions people get backward (floor or vanity first, paint or tile first), and the purchase dates that keep the crew from standing still.

October 18, 2026 · 7 min read

The eleven steps, in order

StepWhat happensIt waits forTypical time
1. Choose and orderVanity, tub, shower valve, toilet, tile and trim, fan, lights, permitNothing; this is the step that gets skipped2 to 8 weeks before demo
2. DemoDown to studs and subfloor; old tile, board, tub outThe long-lead items ordered; a dumpster1 to 2 days
3. Framing and blockingFix rot, move walls, build the niche, add blocking for grab bars, towel bars, glass and the vanityFinal fixture choices and their spec sheets1 to 3 days
4. Rough plumbing and electricalDrain, supplies, valve body, vent; GFCI circuits, fan duct to the outside, light boxes, heated-floor circuitThe vanity, tub and valve chosen; the valve body on site2 to 4 days
5. Rough inspectionInspector sees pipes and wires before anything covers themA booked slot, often 2 to 5 days out1 visit
6. Set the tub, insulateAlcove or drop-in tub set and leveled; exterior walls insulatedA passed rough inspection1 day
7. Wall board and waterproofingCement or foam board in the wet zone, moisture-resistant drywall elsewhere; shower pan and membrane; flood testThe tub in place; the board lips over its flange3 to 5 days, including the 24-hour flood test
8. TileShower walls and floor, then the bathroom floor; groutWaterproofing passed; all tile, trim and setting materials on site3 to 6 days
9. PaintCeiling and walls, primer and two coatsTile and grout done1 to 2 days
10. FixturesVanity and top, toilet, faucet and shower trim, lights, fan grille, mirror, accessoriesPaint dry; every fixture on site2 to 3 days
11. Glass, caulk, finalShower glass measured and installed, final caulk, final inspection, punch listFinished tile (glass is measured off it)2 to 4 weeks of wait for the glass, half a day to install

The working days add up to roughly three to five weeks; the waits between them stretch it to six to nine. Where that calendar time goes, week by week, is in how long a bathroom remodel takes. This guide is about the order, and why it cannot be shuffled.

Rough plumbing is where a late decision becomes a change order. The plumber sets the shower valve at a depth that matches your finished wall thickness, puts the vanity drain at the height your vanity needs, and positions the toilet flange for its rough-in (12 inches from the finished wall is standard; 10 and 14 inch toilets exist). Every one of those numbers comes from a product you have chosen. Changing the vanity after the walls are closed means opening them again.

What has to be decided before the walls open

  • The shower valve, by brand. The valve body goes in the wall at rough-in, and the trim you see later must come from the same maker and the same valve family. Pick the faucet look first, then buy its matching valve body.
  • The vanity, with its spec sheet. Width, drain height and supply positions set the rough plumbing. A wall-hung vanity also needs blocking in step 3. Lead times run from days to two months; the breakdown is in bathroom vanity lead times.
  • The tub, physically on site. An alcove tub is set before the wall board, because the board laps over the tub’s flange. Measure the doorways too; a 60 inch tub fits through most, a cast iron one needs three people.
  • Anything recessed or wall-mounted. A recessed medicine cabinet, a niche, grab bars, a heated towel bar and the glass door hinges all need framing or blocking that only exists in step 3.
  • The light layout. Sconce boxes beside a mirror are placed from the mirror width and the vanity height, so the mirror is a step-1 decision even though it goes up in step 10.

The four questions people get backward

QuestionUsual answerWhy
Floor tile or vanity first?Floor tile first, under the vanity footprintThe vanity can be replaced later without a tile patch; tiling around it locks you into that exact size
Paint or tile first?Tile first, then paintTile work scuffs walls and the grout haze lands everywhere; paint covers the board edges and the transitions
Paint or vanity first?Paint first, then vanityPainting behind a vanity is the hardest wall in the house to reach; touch-ups come after
Toilet before or after the floor?AfterThe toilet sits on the finished floor, and the flange should sit on top of it; set the flange height for the tile thickness

The paint step is short, and the choice inside it matters more than the timing: bathrooms need a finish that tolerates steam, usually satin or semi-gloss with a mildew-resistant formula. If you want low odor in a small, closed room, a zero-VOC bathroom paint is worth the look; what the labels actually promise is in low-VOC paint: what matters.

What waits, and how long

ItemWaits forHow long
Shower glassFinished, grouted tile; it is measured off the real walls2 to 4 weeks of fabrication after the measure
Using the showerGrout and caulk cureAbout 72 hours for cement grout, 24 hours for most silicone
Sealing the groutGrout cure, per the grout makerTypically 48 to 72 hours after grouting
Mirror and accessoriesVanity, lights and paintLast day of fixtures
Final inspectionEvery fixture working, fan venting outsideBook it when the glass date is known

The buying order is not the work order

Fixtures go in at step 10 but are bought at step 1, because their dimensions are needed at step 4. The rule is the same one that runs a kitchen (the kitchen renovation order has the long version): order by the step that needs the item’s numbers, not by the step that installs it.

ItemIts numbers are needed atOn site byTypical lead time
Shower valve bodyRough plumbingRough plumbingIn stock to 2 weeks; matte black and brass finishes longer
TubRough plumbingBefore wall board1 to 3 weeks; freestanding and cast iron 4 to 8
VanityRough plumbingFixturesStock days to 2 weeks; semi-custom 4 to 8
ToiletBefore demo (measure the rough-in)FixturesIn stock to 2 weeks
Exhaust fanRough electricalRough electricalIn stock
Heated-floor mat and thermostatRough electricalBefore tile1 to 2 weeks
Tile, trim and setting materialsFraming (niche size, tile layout)Before tileStocked 1 to 2 weeks; special order 2 to 6
Shower glassAfter tileStep 112 to 4 weeks after the measure

The tile order is two numbers, not one: the tile itself, and the grout, thinset and trim that go with it. The tile count for the wet zone is in how much tile for a shower, and the bags and buckets underneath it are in how much grout and thinset do I need. Whether the job needs a permit at all, which decides step 5, is in do you need a permit to remodel.

Three habits that keep the order intact

  • Hand the plumber spec sheets, not product names. A printed sheet with the drain height and valve depth is what sets the pipes; a model number read over the phone is how a drain ends up two inches low.
  • Photograph every wall before it closes. Pipes, wires, blocking, with a tape measure in the frame. The photo is how you hang a towel bar in five years without finding a pipe.
  • Nothing is installed until it is all on site. A missing shower trim kit stalls step 10; a missing trim piece of tile stalls step 8. Check every box when it arrives, not on the morning it is needed.

Choose first, rough in to the choices, close the walls, finish from the floor up, and let the glass come last. The sequence is the schedule.