The timeline from tile to first shower
| Step | Typical time | Notes |
|---|---|---|
| Tile and grout finished | Day 0 | Walls, curb, bench and niche all complete |
| Field measure | Within a few days, if it was booked ahead | 30 to 60 minutes on site |
| Quote approved and deposit paid | 1 to 3 days | Fabrication does not start until this is signed |
| Fabrication and tempering | 1 to 3 weeks | Longer for coatings, low-iron glass, notches and special finishes |
| Install | 2 to 4 hours | Two installers for most doors |
| Silicone cure | About 24 hours | No water on it until then |
The total is commonly 2 to 4 weeks, and it starts on the day the tile is done, not the day the bathroom was designed. That makes the glass the last long wait in most bathrooms, and the reason a room that looks finished still cannot be used the way it was drawn. Where it falls against the rest of the job is in how long a bathroom remodel takes.
Why the measure waits for finished tile
Tempered glass is cut, drilled and notched first and heat treated afterward. Once it is tempered, any attempt to trim it shatters the panel. The fabricator therefore needs the real opening, to about an eighth of an inch, and the real opening does not exist until the tile is on the wall. Backer board, mortar and tile add thickness that varies from wall to wall, and almost no wall is perfectly plumb. A frame can hide a quarter inch of error; frameless glass has nothing to hide it with, so the panel is cut to match the wall, lean and all.
What has to be finished before the measure
- All wall tile, set and grouted. Including the row at the ceiling or the top of the glass line, and any trim pieces at the edges.
- The curb or threshold. The finished top, with its slight slope into the shower so water runs back in. Many glass shops ask for about 5 degrees. A level or outward-sloping curb is the most common reason a new door leaks.
- Benches, half walls and niches. Glass that lands on a bench or a knee wall is notched to fit it, and the notch is measured from the finished surface.
- The shower floor. A curbless shower is measured from the finished floor tile, because the door sweep rides on it.
- The valve trim and the fixtures nearby, or at least their exact positions. The measurer checks that the door clears the handle, the vanity and the toilet when it swings.
Paint, mirrors and accessories do not need to be done. The wait between setting tile and grouting, and between grouting and anything else, is covered in how long tile needs to cure.
Book the measure before the tile starts. Glass shops often schedule field measures a week or two out. If you call on the day the grout is done, that week is added to the fabrication time. Call when the tile setter gives a finish date, book the measure for the day after grouting, and move it if the tile runs late.
What has to be decided before the walls close
The glass is ordered last, but two things about it are decided while the studs are still open.
- Blocking for the hinges. A frameless door hangs from two or three hinges screwed through the tile. A 3/8 inch glass door weighs about 5 pounds per square foot, so a 28 by 76 inch door is roughly 70 to 75 pounds, and 1/2 inch glass is about a third heavier. That weight needs solid wood behind it: a doubled stud or flat 2x6 blocking on the hinge side, running the height of the door. Fixed panels held by clips or a channel want blocking too. Backer board and tile alone will not hold a hinge screw for long.
- Which side hinges, and which way it swings. Residential codes based on the IRC require a hinged shower door to open outward, with a clear opening of at least 22 inches. Check that the open door does not hit the toilet, the vanity or the towel bar, and that you can reach the valve without standing under the water.
- What the hinge wall is tiled with. Hinges and clips sit flat on the tile. A raised accent band, a pencil liner or glass mosaic at hinge height forces the installer to shim or to drill through a material that cracks easily. Keep the hinge line on flat field tile.
These belong on the framing and rough-in walk-through, well before tile. The full sequence is in the order of a bathroom remodel.
What you choose at the measure
| Choice | Common options | What it changes |
|---|---|---|
| Glass thickness | 3/8 inch (standard), 1/2 inch | Half inch feels more solid, weighs and costs more |
| Glass type | Clear, low-iron, frosted, patterned | Low-iron removes the green tint against white tile and can add lead time |
| Hardware finish | Chrome, brushed nickel, matte black, brass | Match the faucet finish; special finishes can add a week or more |
| Protective coating | Factory or shop applied | Easier cleaning in hard water; applied before install |
| Layout | Single door, door and panel, fixed panel only | A fixed panel alone is the least expensive and has no hinges |
Settle the hardware finish before the measurer arrives, so the quote can be approved that day. Each day a quote sits unsigned is a day added to the wait.
What it costs
Prices vary widely by region and by shop, but as a rough guide a single frameless door installed commonly runs $900 to $1,500, a door with a fixed panel $1,200 to $2,500, and a larger corner or steam enclosure $2,500 to $4,000 or more. Half inch glass, low-iron glass, notches around a bench and special finishes each add to it. Get the number early enough to sit in the budget beside the tile, because it is often quoted after everything else has been spent. The tile itself is in how much tile a shower needs.
Using the shower in the meantime
Once the grout and silicone have cured, the shower can be used before the glass arrives. A tension rod and a curtain cost a few dollars and need no holes. Keep the spray pointed away from the opening, and take the rod down before install day. If this is the only bathroom in the house, that curtain is what turns a three week wait into an inconvenience instead of a hotel bill.
Put the blocking in at framing, book the measure when the tile gets a finish date, and sign the quote the day it arrives. Those three moves are the difference between two weeks without glass and five.